ESTADO GENERAL DEL PROYECTO
Column
Cronograma

PLANIFICACION
Datos
- Avance Planificado
- Avance Real
- Avance Temporal
Grafico

COSTOS
Datos
- Presupuesto de obra
- Presupuesto erogado
- Presupuesto final a termino
- Avance financiero
| Cuatrimestre 1 |
$2.827.486.693,58 |
$2.720.977.795.88 |
$2.681.660.372.73 |
0.962 |
1.015 |
| Cuatrimestre 2 |
$5.654.973.387,17 |
$5.679.862.390,17 |
$ 5.522.352.893,35 |
1,004 |
1,029 |
| Cuatrimestre 3 |
$8.482.460.080,75 |
$8.504.914.182,87 |
$ 8.422.067.978,07 |
1,003 |
1,010 |
| Cuatrimestre 4 |
$11.309.946.774,33 |
$11.382.601.790,03 |
$ 11.422.647.583,14 |
1,006 |
0,996 |
| Cuatrimestre 5 |
$14.137.433.467,92 |
$14.289.682.992,85 |
$ 14.275.432.715,57 |
1,011 |
1,001 |
| Cuatrimestre 6 |
$16.964.920.161,50 |
$16.979.132.331,20 |
$ 17.222.278.797,84 |
1,001 |
0,986 |
Grafico